Update on the progress on User Stories @ 22.10.2015
US 1 - completed MB: issue #845 to be verified.
- Link: #66
US 2 - completed
- Link: #67
US 3 - completed
- Link: #68
US 4 - completed
- Link: #69
US 5 - completed
- Link: #244
US 6 - completed
- Link: #245
US 7 - completed (is verified after refoctoring, need to be demonstrated)
- Link: #246
US 8 - in progress (to be tested)
- Link: #247
- Filter is not tested. Work around will be use as long no well tested funktion is provided.
- Issue 854 needs to be fixed
US 9 - in progress (to be tested)
- Link: #248
- Movement Authority request to be positioned in the right coordinated system. Testing of Movement Authority correction will be tested by@JakobGärtner. Work in progress for implementing and test on the 22nd of october. BJ: DMI planning area to be tested today. PF: DMI interacing ready for test; BJ: Speed supervision ready for test.
US 10 - open
- Link: #249
- Level Change change from Level 2 to NTC should work and needs to be tested.(Marielle Petit Doche)
- Train will be supervised in ATB mode in the same pattern as in the beginning in Amsterdam. Can be tested (Jakob Gärtner)
US 11 - open
-
Link: #250
-
Level Change from Level 2 to NTC is implemented and needs to be tested. (Mariellle Petit Doche)
US 12 - open
- Link: #251
- RBC message to teminate radio session is implemented (Johannes Kastner)
- Termination of Communication is implemented in MoRC (Uwe Steinke)
US 13 - open
-
Link: #70
-
Track Model to simulate the scenario has been started (Jakob Gärtner).
-
How to bring the Onboard Unit in the right status needs to be clarified (Jakob Gärtner)
-
RBC Model to simulate the scenario needs to be started. (Johannes Kastner)
-
Braking Curve Model needs to be tested according to the US (Thorsten Schulz)
US 14 - open
- Link: #71
- Track Model to simulate the scenario has been started (Jakob Gärtner).
- How to bring the Onboard Unit in the right status needs to be clarified (Jakob Gärtner)
- DLR will deliver implementation of the User Story (Marc Behrens)
- RBC Model to simulate the scenario needs to be started. (Johannes Kastner)
- Mode and Level Management needs to be tested (Marielle Petit Doche)
- DMI Controller and Management needs to be tested (Baseliyos Jacob)
- Environment model to brake release needs to be tested (Stefan Karg)
- Braking Curve Model needs to be tested according to the US (Thorsten Schulz)
- MB: test model work in progress with RT-tester (@Mairamou to be contacted)
- RL: "Change of
US 15 - open
- Link: #72
- Track Model to simulate the scenario has been started (Jakob Gärtner).
- How to bring the Onboard Unit in the right status needs to be clarified (Jakob Gärtner)
- RBC Model to simulate the scenario needs to be tested. (Johannes Kastner)
- Mode and Level Management needs to be tested (Marielle Petit Doche)
- DMI Controller and Management needs to be tested (Baseliyos Jacob)
- Environment model to brake release needs to be tested (Stefan Karg)
- Braking Curve Model needs to be tested according to the US (Thorsten Schulz)
US 16 - open
-
Link: #73
-
Track Model to simulate the scenario has been started (Jakob Gärtner).
-
How to bring the Onboard Unit in the right status needs to be clarified (Jakob Gärtner)
-
RBC Model to simulate the scenario needs to be tested. (Johannes Kastner)
-
Mode and Level Management needs to be tested (Marielle Petit Doche)
-
DMI Controller and Management needs to be tested (Baseliyos Jacob)
-
Environment model to brake release needs to be tested (Stefan Karg)
-
Braking Curve Model needs to be tested according to the US (Thorsten Schulz)